RC EAST: 011235Z Bagram PRT Kapisa QA/QC
The Bagram PRT Kapisa team conducted Q/A &. amp ...
|
|
RC EAST: 101230Z Bagram PRT Parwan QA/QC
The Parwan team conducted a QA/QC on Qalander Khil Rd, Flood 1,2 and conducted a clinic assessment on the Qalander Khil Clinic.
|
|
RC EAST: 111240Z Bagram PRT Parwan QA/QC
The mission for today was to be Gowl-e-Khil Rd. The Parwan team only made it to the Sia Gird District Center ...
|
|
RC EAST: 120315Z Bagram PRT Kapisa QA/QC
On December 12, 2007 the Kapisa team met with the Kohband sub-governor and the shura leader at the Kohband District Center to discuss development needs for the district.
|
|
RC EAST: 120330Z Bagram PRT Parwan QA/QC of Dandaar Road
Today December 12 2007, the Parwan team conducted a QA on the road from the ANP CP into Dandar.
|
|
RC EAST: 130330Z Bagram PRT Parwan QA/QC
The Parwan Team with USAID performed an initial assessment of the hydro-electric power plants located in Charikar City and JabulSaraj.
|
|
RC EAST: 170315Z Bagram PRT Parwan QA/QC
On December 17, 2007 the Parwan team conducted QA&. apos ...
|
|
RC EAST: 180300Z Bagram PRT Kapisa Mahmoud Raqi QA/QC
On December 18, 2007, the Kapisa team conducted a mission to the Deh Baba Ali Bazar to conduct an assessment of the Bazaar and meet with some key leaders.
|
|
RC EAST: 180415Z Bagram PRT Clinic Assessment & QA/QC
On December 18, 2007, the Parwan team conducted Road assessment on the following roads: Ofian-e-sharif, andTotumundare roads. The first stop was ofian-esharif road ...
|
|
RC EAST: 190320Z Bagram PRT Bagram QA/QC
On 19 December the Parwan Team preformed a QA/QC at Granshakh School in eastern Bagram District.
|
|
RC EAST: 190400Z Bagram PRT Kapisa QA/QC
On 19 December the Kapisa team entered the Panjshir River bed at the village of Sayad in Mahmood Raqi in order to conduct a flood wall assessment. Last Spring the area was hit very hard by flooding and many farmers fields were destroyed, homes were washed away, and lives were threatened ...
|
|
RC EAST: 200315Z Bagram PRT Kapisa Clinic QA/QC
The Kapisa team traveled to Kohistan I to conduct an assessment of the Anwar Khan Kheyl Health Clinic and the Gulbahar Health Clinic. Both of these clinics are controlled by NGO& ...
|
|
RC EAST: 220330Z Bagram PRT Parwan QA/QC
The Parwan Team executed a ground convoy to assess construction projects, clinics, and the Salang Tunnel in the Salang District of Parwan Province.
The first stop was at the site of the Salang District Center project located just north of the Salang High School ...
|
|
RC EAST: 220434Z Bagram PRT Nijrab QA/QC
Kapisa team conducted a QA/QC of the Farukh Shah BHC and High School.
|
|
RC EAST: 240330Z Bagram PRT Parwan Hospital Assessment of Totumdara-e-Olia Clinic
The Parwan Team executed a ground convoy in cooperation with TF Med and the CJTF 82 Surgeon&.
|
|
RC EAST: 240330Z Bagram PRT Kapisa PDM Mahmood Raqi
Kapisa team attended the PDC meeting in conjunction with Cincinnatus to discuss development and security in Kapisa.
|
|
RC EAST: 260000Z Bagram PRT Parwan Charikar City Ribbon Cutting
On December 26 the Parwan team travelled to Charikar City, Ophyan-e-Sharif (IVO 42S WD 150 775), and Totumdarah Ulya (IVO 42S WD 180 820).
|
|
RC EAST: 260330Z Bagram PRT Kohistan II CHC Ribbon Cutting
Kapisa team attended the ribbon cutting for two projects in Kohistan II, Aftabachi Girls School and Qazaq Comprehesive Health Clinic. The deputy governor attended along with the health director, the school principle, and many village elders ...
|
|
RC EAST: 29 0300Z Bagram PRT QA/QC of Jurghati, Kohi Safi district
The Parwan conducted a HA drop and water system project quality inspection in Jurghati, Kohi Safi district.
|
|
RC EAST: 310300Z Bagram PRT Bagram District Center QA/QC
The Parwan Team travelled to the Bagram District Center to survey the progress on the new district center as well as document the completion of the school book storage container foundation at the high school next door.
|
|
RC EAST: 010330Z TF Cincinnatus Bagram PRT QA/QC of of Chardeh Girls School
1 Jan 2008:
The team started the mission on 1 Jan and quickly encountered the contractor widening the Ghorband Pass road at Pule-matak (IVO 42S WD 1880 6300).
|
|
RC EAST: 06 Jan 08 TF BAYONET PRT Mehtar Lam PRT/CA Daily Activity
06 Jan 08 PRT Mehtar Lam PRT/CA Daily Activity
Last 24: QA/QC mission to Dowlet Shah district.
|
|
RC EAST: 070425Z TF CINCINNATUS Bagram PRT Kohistan I QA/QC Water Piping System & meeting with the Governor
On 7 January, the Kapisa team met with the Kohistan I subgovernor to discuss future projects in the district. The sub-governor led us to the location we were considering for a water piping system and we got the grid coordinates it ...
|
|
RC EAST: 080430Z TF CINNCINNATUS Bagram PRT KLE meeting in Jabulusaraj
Conducted meeting with Governor Taqwa, Deputy Governor Salangi, Deputy Shura Leader Salangi regarding the BAF western expansion plan.
|
|
RC EAST: 080430Z TF CINNCINNATUS Bagram PRT Meeting in Jablusaraj
The Parwan Team travelled to Jablusaraj to meet with the Sub Governor to discuss the gabion retaining wall project. The meeting began with a discussion of the plan to create a retaining wall behind the bazaar in town to avoid losing it in the spring flooding ...
|
|
RC EAST: 090430Z Bagram PRT Recon of Monarach Road
Trip Report 9 Jan 08. Recon Snow & ...
|
|
RC EAST: 100400Z TF Cincinnatus Bagram PRT Kohband Clinic Assessment
Kapisa team conducted a QA/QC of the new Kohband District Center and the Sanjan Basic Health Clinic in Kohistan I.
|
|
RC EAST: 100415Z TF Cincinnatus Bagram PRT Site Survey in Sayed Khail District
The Parwan team set out today to perform site surveys for new construction for two schools, a security wall for a new district center complex, and a new clinic.
|
|
RC EAST: 100415Z TF Cincinnatus Bagram PRT ANP Assessment in Jabulsaraj
On Janurary 10, the PTAT team and combat camera personnel made a visit to Jabulsaraj district center and ANP station.
|
|
RC EAST: 121506Z TF BAYONET Mehtar Lam PRT Daily Activity
Last 24: The PRT Engineers met with contractors at the FOB regarding ongoing projects.
|
|
RC EAST: 140430Z TF CINCINNATUS Bagram PRT Assessment of Bagram Granshakh School
The Parwan Team executed a ground convoy to assess the construction progress on Granshakh School as well as a clinic site assessment and a functional assessment of an existing clinic.
|
|
RC EAST: 14 Jan 08 TF BAYONET Mehtar Lam PRT Daily Report
Last 24: QA/QC today at Kudagal Valley Bridge.
|
|
RC EAST: 150430Z TF CINCINNATUS Bagram PRT Assessment of Qualeh Yuzbashi windmill in Kohi Safi
Today the Parwan CAT did a QA on the Qualeh Yuzbashi windmill well, and went to Kohi Safi to QA Range Road to the ANP CP and had a meeting with the District Chief concerning additional road clearing.
|
|
RC EAST: 160420Z TF Cincinnatus Bagram PRT Assessment of Bagram Marked Rd. Rabat Clinic, Womens admin Bldg, & the Charikar Orphanage
16 Jan 08 Mission: The first stop was at Bagram Market Road to conduct an QA/QC on the road project.
|
|
RC EAST: 170430Z TF CINCINNATUS Bagram PRT Provential Development Meeting & Humanitarian Assistance
The Parwan Team executed a ground convoy to attend a development meeting with the Parwan Director of Education and his engineering staff, To perform a facility site assessment at the Charikar Hospital, and to complete delivery of blankets for the children at the Charikar orphanage.
|
|
RC EAST: 190500Z TF Cincinnatus Bagram PRT Assessment of Qalander Khil Road
On 19 January, the Parwan team conducted QA/QC of Qalander Khil Road on 19 Jan 08.
|
|
RC EAST: 20 Jan 08 TF BAYONET Mehtar Lam PRT Daily Activity
Today: QA/QC of projects in Alishang district.
|
|
RC EAST: 210415Z TF Cincinnatus Bagram PRT Provicial Counsel meeting in Mahmood Raqi
On the 21 January, the Kapisa was schedule to attend a meeting with the Provicial Counsel meeting, but it did not happen today as the counsel member who was supposed to set up the meeting forgot about our appointment.
|
|
RC EAST: 210515Z TF Cincinnatus Bagram PRT Meeting with the sub governor at the Sayed Khail District Center
On 21 January, the Parwan Team executed a ground convoy to meet with the Ministry of Public Works, Salang Regional Maintenance Chief, Colonel General Eng.
|
|
RC EAST: 220510Z TF Cincinnatus Bagram PRT Clinic Assessment in Tajiki Kafshan Shinwari
On 22 January, The Parwan team conducted a QA/QC and clinic assessment in Tajiki Kafshan.
|
|
RC EAST: 280510Z TF Cincinnatus Bagram PRT Education Meeting in Charikar
On 28 January the Parwan team Met with Deputy Salangi at the Ministry of Education building in Charikar. Topics of discussion were the Gulak boys and girls school, Surka Parsa, Granshakh School, Bagram, Bakshil Kheyl and Jan Qadan schools, Bagram and Center of Excellence site survey ...
|
|
RC EAST: 300530Z TF Cincinnatus Bagram PRT QA/QC of the three CSTC-A projects in Kapisa
The Parwan team conducted QA/QC of the three CSTC-A projects in Kapisa.
|
|
RC EAST: 310510Z TF Cincinnatus Bagram PRT Meeting with the Chief of Education in Salang
Met with Allim Mojoddadi, Salang District Leader and Gulam Haidar, Salang Chief of Education. Today we discussed the location for the new Salang Girls School ...
|
|
RC EAST: 090515Z TF Cincinnatus Bagram PRT Provincial Development Meeting & QA/QC in Nijrab
Conducted mission to several destination. 1st attend a PDM , 2nd Q/A of 3 CSTC-A project one in Nijrab and 2 in Tagab and also a PRT project in Nijrab ...
|
|
RC EAST: 110430Z TF Cincinnatus Bagram PRT Mahmood Raqi Girls School & Broadcasting Training
Kapisa team conducted a mission to the Mahmood Raqi Radio Station to train the personnel that work at the station. AFN personnel and the IO officer assisted in the training ...
|
|
RC EAST: 120525Z TF Cincinnatus Bagram PRT Assessment of Granshakh School with the Parwan Department of Education
The Parwan team conducted a QA/QC of Granshakh School with the Parwan Department of Education and the Amari Construction Company.
|
|
RC EAST: 081230Z, TF BAYONET PRT NANGARHAR, CE Notes for Team Nangarhar Mission to Hiserak District
SUBJECT: Trip Report CE Notes for Team Nangarhar Mission to Hiserak District
1. SUMMARY ...
|
|
RC EAST: 140610Z TF Cincinnatus Bagram PRT QA/QC in Nijrab
Kapisa team went to Nijrab to QA/QC three projects.
|
|
RC EAST: 150732z TF 3 Fury Reports: PMTP Paktya ANP Station Assessments
1. Met with engineer Montage, the foreman for the contractors from Toifor installing the LSS units at the Waze Zadran SWD 27447 87880 in which we delivered 25 mattress to be use for the female dorm at the University grid 42SWD 27287 87575 and along with us were some media from the discovery channel to document us give it to the University, from there we convoyed to the Shairkhan Kheyl CHC grid 42SWD 27032 88528 to do a HA drop for the children at the CHC, from there were going to do other HA drop but I made the call not to go there and instead RP back to BAF ...
|
|