Summary |
Details |
RC EAST: 080430Z, TF Bayonet PRT NANGARHAR CE TRIP REPORT TO BATI KOT, GHANI KHEL, ACHIN AND KOT
SUBJECT: Trip Report for Bati Kot, Shinwar, Achin, &. amp ...
|
|
RC EAST: 180510Z TF Cincinnatus Bagram PRT QA/QC at the Basic Health Clinic in Malikar Kohband
Kapisa team went to Kohband to QA/QC the Basic Health Clinic in Malikar.
|
|
RC EAST: 190430Z TF Cincinnatus Bagram PRT Meetinf at the Alasay District Center
Kapisa team linked up with Pathfinder and two Apaches and conducted a joint operation to the Alasay District Center. We called the sub-governor as we were departing FB Kutshbach and told him we would be arriving in 30 minutes ...
|
|
RC EAST: 190510Z TF Cincinnatus Bagram PRT Assessment of the Jabulsaraj Basic Health Clinic
The Parwan team conducted an assessment of the Jabulsaraj Basic Health Clinic today. The BHC burnt down two weeks ago ...
|
|
RC EAST: 200534Z TF Cincinnatus Bagram PRT Agriculture Meeting in Charikar
Parwan Team took members of the Nebraska National Guard Agriculture Team for an area recon of the Parwan Province agriculture facilities. The Agriculture Team was able to tour four facilities ...
|
|
RC EAST: 22 Feb 08 TF Bayonet Mehtar Lam PRT Daily Activity
Today: A three day mission to Alishang District concluded today. QA/QC projects and village engagements were the goal of this mission ...
|
|
RC EAST: 230540Z TF Cincinnatus Bagram PRT KLE & Meeting with Sub Governor + CSTCA projects in Nijrab
Kapisa team traveled to Nijrab District to QA/QC 3 projects and to coordinate the movement of 2 containers at Morales Frazier.
|
|
RC EAST: 230625Z TF Cincinnatus Bagram PRT QA/QC Qalander Khil Road in Bagram
Today the Parwan CAT conducted a QA/QC with the RRP on Qalander Khail Road, and went to Jabulsaraj to see the progress of the Gabion walls.
|
|
RC EAST: 24 Feb 08 TF Bayonet Mehtar Lam PRT Daily Activity
Today: A QA/QC mission in Mehtar Lam District visited several projects in the district today.
|
|
RC EAST: 250610Z TF Cincinnatus Bagram PRT QA/QC Totamdarah and Ophian-e-Sharif Road in Jabulsuraj
Parwan Team conducted QA/QCs of Ophyien-y-Sharrif and Totumdarah roads.
|
|
RC EAST: 260430Z TF Cincinnatus Bagram PRT Gulbahar L Recon & ANA Depot in Bagram
The Parwan Team convoyed to the Bagram District Center and attended the placement of the first set of school book storage containers in the joint PRT, DANIDA, and Ministry of Education project to place book storage locations in all districts of Parwan.
|
|
RC EAST: 270445Z TF Cincinnatus Bagram PRT Teacher Training Facility in Charikar
Parwan Team traveled to the Teacher Training Facility in Charikar. The students are on break right now and will begin classes again on April 2nd ...
|
|
RC EAST: 27 Feb 08 TF Bayonet Mehtar Lam PRT Daily Activity
Today: A mission to Alingar District today took place to QA/ QC projects in the district.
|
|
RC EAST: 280430Z TF Cincinnatus Bagram PRT Assessment of projects in the Nijrab District
Kapisa team traveled to Nijrab District to do an inspection of the Winter School Program. Our first stop was Abdul Sabur School ...
|
|
RC EAST: 03 1413Z TF Bayonet Mehtar Lam PRT Daily Activity
Today: A QA/QC mission to check the status of projects in the Alishang District took place today.
|
|
RC EAST: 070510Z TF Cincinnatus Bagram PRT QA/QC''s in Nijrab
Kapisa team went to Nijrab to conduct QA/QCs, conduct RIP/TOA with the new PRT, and conduct a KLE with the sub-governor.
|
|
RC EAST: 08 1356Z TF Bayonet Mehtar Lam PRT Daily Activity
Today: A QA/QC GAC was conducted to the Alishang District.
|
|
RC EAST: 09430Z TF Cincinnatus Bagram PRT QA/QC of projects in Kohistan Area
Kapisa team conducted a mission to the Kohistan II and Kohband district to conduct KLEs and to introduce the new team leaders to the sub-governors and to view PRT projects in those districts.
|
|
RC EAST: 09 1704Z TF Bayonet Mehtar Lam PRT Daily Activity
Today: Left seat/Right seat continues. A QA/QC mission to Mehtar Lam district was scheduled to check progress of projects in the Mehtar Lam District ...
|
|
RC NORTH: 160400Z TFCINCINNATUS PANJSHIR PRT ENGINEERS QA/QC INSPECTION
Panjshir, PRT Engineers: Conducted QA/QC of the Shaba Basic Health Clinic Repair.
|
|
RC EAST: 160510Z TF Cincinnatus Bagram PRT Recon of FOB Pathfinder in Tag Ab
Team Kapisa conducted a convoy enroute to Tag Ab to conduct a QA/QC of the Tag Ab District Center and recon FB Pathfinder.
|
|
RC EAST: 160630Z TF CINCINNATUS PANJSHIR PRT ENGINEER KLE MEETING
PRT Engineers conducted QA/QC of Anaba Irrigation Canal (Anaba.
|
|
RC EAST: 170030Z TF Cincinnatus Bagram PRT QA/QC of hydroelectric plant in Jabalsuraj
We rolled in a four vehicle convoy to the area close to ECP 3 and the Bazaar on post. We met with a group of four individuals from Army Corps of Engineers in a LAV ...
|
|
RC EAST: 180500Z TF Cincinnatus Bagram PRT QA/QC of Heavy Equipment for Salang Pass Maintenance in Jablusaraj
We rolled in a four vehicle convoy to Jablusaraj to meet with LTG Rajab, who works for the Department of Public Works and is responsible for maintaining a fleet of heavy earth moving equipment to keep the Salang Pass open year round.
|
|
RC EAST: TF CINCINNATUS Dara/Rokha QA/QC
We conducted an initial site review for the Dara Micro-Hydro Repair. Farid Redwan Construction Company, a Dara District Manager Representative, and engineers recommended tie-in points for the weir and canal which would make the weir length 40m ...
|
|
RC EAST: TF CINCINNATUS Shutol QA/QC
Dehe Kalaan Clinic Access Road was recently awarded through CERP. Capt McGinnis, Shutol District Manager, and Yakoubi CC met for an intial site review and agreed on the clinic access road& ...
|
|
RC EAST: 230700Z TF CINCINNATUS PANJSHIR PRT KLE MEETING
PRT Engineers: Met with Shutol District Manager and Yakoubi Dehe Kalaan Clinic Access Road.
|
|
RC EAST: 230700Z TF CINCINNATUS PANJSHIR PRT KLE MEETING
PRT Engineers:
Panjshir, PRT Engineers met with Dr.
|
|
RC EAST: TF CINCINNATUS Anaba QA/QC
Met with Dr. Wajeed (Anaba PC member) to discuss repair of Anaba Micro-Hydro plant (40 KW) damaged by last years flood ...
|
|
RC EAST: 240430Z TF Cincinnatus Bagram PRT Parwan Team Civil Recon in Kohi Sofi
We rolled in a three vehicle convoy to southern Kohi Safi. Our mission was to conduct a rural reconnaissance of the villages between Dandar and Nilay ...
|
|
RC EAST: 240500 TF Cincinnatus Bagram PRT Kapisa Team Civil Recon in Nijrob
The team moved out in a three vehicle convoy at 0800 with an agenda to stop at the Nijrob District center to conduct link up with the Sub Governor and some ANP who had agreed to provide the team an escort and guide into the Villages of Sagay and Pajan so the team could conduct a Civil Reconnaissance mission.
|
|
RC EAST: Initial Site QA/QC
Khenj Judicial Building and Book Storage initial site review
Arie Koh Construction and SSCC both met at Khenj District Center.
We wanted to ensure that the District Manager is well aware that there will be three construction projects within 30 m of the District Center ...
|
|
RC EAST: 260430Z TF Cincinnatus Bagram PRT Kapisa Team Civil Recon in Nijrab
Team Kapisa:
Destination #1 Nijrob
Mission: Conduct Civil Reconnaissance of the Nijrob District Center Bizarre
Task: Conduct face to face Civil Reconnaissance in the Nijrob District Center Bizarre market.
|
|
RC EAST: 260700Z TF CINCINNATUS PANJSHIR PRT KLE MEETING
Panjshir PRT Engineers: Meeting with Shadow Louis Berger Group to identify critical road repair.
|
|
RC EAST: 261352Z TF CINCINNATUS
Louis Berger Group Warranty Review
George Martin (Manager of LBG) briefed the commander and engineers on the operation and road maintenance program.
|
|
RC EAST: 270700Z TF CINCINNATUS PANJSHIR, PRT KLE MEETING
Panjshir, PRT Engineers: Shotol Clinic Road final site resolved. Road work should be completed w/in 10 days
Bakhshikel Vehicle Bridge (Rokha) and Charmaghza Health Clinic upgrade (Dara) bid evaluations completed selection w/in the next few days ...
|
|
RC EAST: TF CINCINNATUS MICRO-HYDRO SITE SURVEY
Japanese Micro-Hydro Survey
Site survey was 2. 6km from generator house to canal inlet ...
|
|
RC EAST: 290700Z TF CINCINNATUS PANJSHIR PRT KLE MEETING
Panjshir, PRT Engineers: Evaluated/selected bids for the Molakhe Vehicle Bridge and Bakhshikel Vehicle Bridge proposals.
|
|
RC EAST: 290700Z TF CINCINNATUS PANJSHIR PRT KLE MEETING
Panjshir PPT Engineers: Evaluated/selected bids for the Molakhe Vehicle Bridge and Bakhshikel Vehicle Bridge proposals. Utilized teams new best value spreadsheet, and selected the following contractors: Freedom Construction Company for Molakhe Bridge at $175,400 ...
|
|
RC EAST: 300700Z TF CINCINNATUS PANJSHIR PRT KLE MEETING
PANJSHIR, PRT ENGINEERS:
QAQC Obdara HS - estimate completion within 60 days. Contractor was applying paint and installing windows ...
|
|
RC EAST: TF CINCINNATUS PRT PANJSHIR QA/QC
Dara DC meeting
In our meeting w/Dara District Manager (Malam Sorab), we discussed the timeline of the future District Center and sitting the bookstorage ...
|
|
RC EAST: 010430Z TF Cincinnatus Bagram PRT Ground Breaking Ceramony at Basic Health Clinic in Mandikowl Village
The groundbreaking ceremony went very well. Participation was good at about 100 people attending ...
|
|
RC EAST: 020730 TF Cincinnatus Bagram PRT Kapisa Team QA/QC Heavy Equipment in Jabulsaraj
The equipment was not at the location for the second time. The Gen ...
|
|
RC EAST: 030700Z TF CINCINNATUS PANJSHIR PRT ENGINEER QA/QC
PANJSHIR,PRT Engineers:
Paryan Vehicle Bridge final inspection completed. Issue remains with site clean-up ...
|
|
RC EAST: 030700Z TF CINCINNATUS PANJSHIR PRT ENGINEERS QA/QC
PANJSHIR PRT Engineers:
Paryan Vehicle Bridge final inspection completed. Issue remains with site clean-up ...
|
|
RC EAST: TF CINCINNATUS PRT PANJSHIR
Completed Paryan Vehicle Bridge final inspection. District Manager still had issues with site clean-up ...
|
|
RC EAST: 050700Z TF CINCINNATUS PANJSHIR PRT ENGINEERS
PANJSHIR, PRT ENGINEES: Met w/ Saifi Construction on site of Kolacha Irrigation Canal to identify concerns addressed by RRD.
|
|
RC EAST: TF CINCINNATUS PRT PANJSHIR DAMAGER ASSESSMENT
RRD site review
Met w/ Saifi Construction on site of Kolacha Irrigation Canal to identify concerns addressed by RRD.
This project is a $78,607 ...
|
|
RC EAST: 060747Z TF CINCINNATUS PANJSHIR PRT ENGNIEERS
PANJSHIR PRT Engineers: - Met w/ Saifi Construction, RRD, and local elders on site of Kolacha Irrigation Canal to identify concerns.
|
|
RC EAST: 061800 PRT METHAR LAM (LAGHMAN PROVINCE) CA DAILY SPOT REPORT
061800APRIL2008 PRT METHAR LAM (LAGHMAN PROVINCE)
CA DAILY REPORT
BY 1SG JOHNSON
REVIEWED BY MAJ SAMUEL
LAST 24:
--- Executed CONOP to Alingar & FOB Kalagush.
|
|