Identifier
Created
Classification
Origin
09BAGHDAD2021
2009-07-28 11:31:00
UNCLASSIFIED//FOR OFFICIAL USE ONLY
Embassy Baghdad
Cable title:  

RRT ERBIL: NEW REFINERY AND CRUDE PRODUCTION COMES

Tags:  ECON EPET ENRG EINV PGOV IZ 
pdf how-to read a cable
VZCZCXRO8099
RR RUEHBC RUEHDA RUEHDE RUEHDH RUEHIHL RUEHKUK
DE RUEHGB #2021/01 2091131
ZNR UUUUU ZZH
R 281131Z JUL 09
FM AMEMBASSY BAGHDAD
TO RUEHC/SECSTATE WASHDC 4098
INFO RUCNRAQ/IRAQ COLLECTIVE
RHEBAAA/USDOE WASHDC
UNCLAS SECTION 01 OF 02 BAGHDAD 002021 

SENSITIVE
SIPDIS

DOE FOR GEORGE PERSON; STATE ALSO FOR EEB AND NEA/I

E.O. 12958: N/A
TAGS: ECON EPET ENRG EINV PGOV IZ
SUBJECT: RRT ERBIL: NEW REFINERY AND CRUDE PRODUCTION COMES
ON LINE

This is an Erbil Regional Reconstruction Team (RRT) cable.

UNCLAS SECTION 01 OF 02 BAGHDAD 002021 SENSITIVE SIPDIS DOE FOR GEORGE PERSON; STATE ALSO FOR EEB AND NEA/I E.O. 12958: N/A TAGS: ECON EPET ENRG EINV PGOV IZ SUBJECT: RRT ERBIL: NEW REFINERY AND CRUDE PRODUCTION COMES ON LINE This is an Erbil Regional Reconstruction Team (RRT) cable. ¶1. (U) Summary: At a July 18 ceremony, attended by KRG Prime Minister Nechirvan Barzani and former Ambassador to Iraq and the UN Zalmay Khalilzad, oil from the Khurmala Dome began flowing into the Erbil refinery, the only privately-owned refinery in Iraq. The refinery's initial capacity is 20,000 bbl/d, with plans to expand to 75,000 bbl/d by 2010. The Kurdistan Regional Government (KRG) intervened and privatized the project after construction had stalled for two years, and it was completed soon thereafter. Under an agreement between the KRG and the GOI, crude oil from the field will also flow to the pipeline from Kirkuk to Ceyhan in Turkey. The refinery project also entailed a significant purchase of U.S.-origin equipment. End Summary. ¶2. (U) On July 18, after a ceremony attended by Kurdistan Regional Government (KRG) Prime Minister Nechirvan Barzani and the former US Ambassador to Iraq and the UN, Zalmay Khalilzad, oil from the Khurmala Dome began to flow to the brand new Erbil refinery. This is the first large refinery in the Kurdistan Region, and the first privately-owned refinery in Iraq. ¶3. (U) The refinery is operated by KAR Oil and Gas Ltd., a member of the Erbil-based KAR Group, a conglomerate that does engineering and construction projects all over Iraq (over 3,000 to date) in addition to its work in the hydrocarbon sector. KAR group grew quickly after 2003, mostly through its civil engineering contracting work for the U.S. Government around Iraq. It also worked on the rehabilitation of the Kirkuk-Ceyhan pipeline, and claims to have a large proportion of its Iraqi staff outside the Kurdistan Region. ¶4. (U) The refinery is connected to the Khurmala Dome by a 40-kilometer, 20-inch buried pipeline. The refinery has a current capacity of 20,000 bbl/d, and will produce diesel and kerosene, as well as fuel oil for cement and brick factories. A project to expand capacity is already underway, with production expected to double to 40,000 bbl/d by the end of ¶2009. The additional expansion will consist of a distillation unit and process units capable of producing gasoline up to 95 octane. Further plans exist to expand refinery production to 75,000 bbl/d in 2010. ¶5. (SBU) KAR t
ook over the refinery project in late 2008, when it was 60% complete. According to Brad Camp (protect), an American and KAR executive who helped develop the project, the refinery project had actually begun in 2005 as a partnership between the Iraqi Ministry of Oil and the Iraqi Ministry of Industry and Minerals, and was scheduled to be completed in 18 months. However, after the project bogged down due to budgetary and technical problems, the KRG intervened and privatized the project by selling the refinery to KAR, which completed the refinery using its own funds. The investment for all components of the project (see below) totaled $670 million. Processing Facility and Crude Production -------------- ¶6. (SBU) KAR also took over the completion of the Khurmala Dome central processing facility. The KRG awarded a $140 million contract to KAR to complete the facility. Camp said that the reason for the delay in the refinery project was that the GOI-owned Northern Oil Company (NOC) took no action during the two-year period to complete the Khurmala Dome central processing facility that feeds the refinery. This was not because of a standoff in the field, but reportedly Qwas not because of a standoff in the field, but reportedly because of the NOC's ineffectiveness. The equipment that had been purchased sat in storage for two years, and the warrantees were beginning to expire. ¶7. (U) The Khurmala Dome is located in the northern part of the Kirkuk Structure and lies inside the Erbil Governorate. It is approximately 20 kilometers long and 8 kilometers wide. KAR rehabilitated 40 older, capped wells, and built the necessary infrastructure to connect these wells to the central processing facility, which should be able to process 150,000 bbl/d. Any excess oil production beyond that which is needed to feed the Erbil refinery will be exported through the Strategic Pipeline (Kirkuk-Ceyhan) under an agreement reached between KRG Prime Minister Nechirvan Barzani and GOI Oil Minister Shahristani in November 2008. Significant U.S. Sales -------------- BAGHDAD 00002021 002 OF 002 ¶8. (SBU) The refinery project reportedly entailed a large purchase from U.S. company Ventech Engineering, totaling over $125 million. There may be additional follow-on purchases as the project progresses. ¶9. (SBU) Comment: The completion of the Erbil refinery comes less than two months after oil began to flow from the privately-developed Tawke and Taq Taq fields to international markets. The KRG - including PM Barzani in his speech at the event - points to these events as evidence that working in partnership with the private sector is the key to developing the hydrocarbon sector. There are several elements to this project that would appear to be positive for U.S. objectives: development of hydrocarbon production, agreement between Baghdad and Erbil to do so, and promotion of U.S. exports. Thus far, the central government Ministry of Oil (MoO) has not commented on the fact that the refinery is obtaining its oil supply from the Khurmala Dome, which has been an object of contention. The MoO argues that the KRG did not have the right to operate on the field, which is under the geographic responsibility of the North Oil Company but lies in Erbil Province. Khurmala Dome is also geologically a part of the Kirkuk oil field, which straddles the KRG boundary. End Comment. FORD