Identifier
Created
Classification
Origin
08ADDISABABA1229
2008-05-08 11:04:00
UNCLASSIFIED
Embassy Addis Ababa
Cable title:  

WATER SHORTAGE LEADS TO POWER CUTS

Tags:  ECON ENRG SENV ET 
pdf how-to read a cable
VZCZCXRO8411
RR RUEHROV
DE RUEHDS #1229/01 1291104
ZNR UUUUU ZZH
R 081104Z MAY 08
FM AMEMBASSY ADDIS ABABA
TO RUEHC/SECSTATE WASHDC 0505
INFO RUCNIAD/IGAD COLLECTIVE
UNCLAS SECTION 01 OF 02 ADDIS ABABA 001229 

DEPT FOR AF/EPS AND EEB

SIPDIS

E.O. 12958: N/A
TAGS: ECON ENRG SENV ET

SUBJECT: WATER SHORTAGE LEADS TO POWER CUTS

UNCLAS SECTION 01 OF 02 ADDIS ABABA 001229 DEPT FOR AF/EPS AND EEB SIPDIS E.O. 12958: N/A TAGS: ECON ENRG SENV ET SUBJECT: WATER SHORTAGE LEADS TO POWER CUTS ¶1. SUMMARY: Due to lower-than-normal spring (Belg) rains, the Ethiopian Electric Power Company (EEPCO) has instituted a program of rolling power cuts throughout the country. Heavily dependent on hydropower, without improved rains the cuts are expected to expand from two days per week to four in May. Additional effects of the power shortage include telecommunications disruptions and cuts in municipal water supply. END SUMMARY. ¶2. Ethiopia is dependent upon hydropower to generate electricity, with over 663 megawatts (MW) (85%) of the country's total installed generating capacity of approximately 780 megawatts (MW) coming from hydropower. Due to aging plants, only about 700 MW can be reliably generated according the EEPCO's Deputy General Manager (DGM)Melaku Mamo. The DGM also stated that under current operations, 90% of current generation is from hydropower, 9% is from diesel and 1% is from geothermal. In addition to installed capacity, EEPCO is in the process of a massive expansion in hydro-electric power capacity. In the next ten years, ten additional hydropower plants costing over $13 billion will raise the country's generating capacity to 6,588 MW. Ethiopia's demand for electricity remains quite low, about 390 MW. Only 22% of the country geographically is covered by electric service. ¶3. Ethiopia has two rainy seasons - a short season typically lasting from February to April (Belg) and a longer Meher season lasting from May through September. This year's Belg rains were delayed and did not begin until April. Since they began, they have been spotty and erratic, leading to drought conditions in much of the country and a shortage of water to power hydropower plants, which has caused production to decline to approximately 311 MW, an 80 MW power deficit. Currently, EEPCO is running an additional 32 MW of diesel generators to attempt to make up the gap at a reported cost of 100 million birr per month (about $10 million). This is not sufficient to meet demand, and in April EEPCO instituted two day per week, 12 hour per day cuts on a rolling basis throughout the country. These cuts were expanded in early May to five days every two weeks. EEPCO's DGM told EconOff on a recent site visit to the country's only (and currently non-functioning) geothermal power plant that if the Meher rains do not begin in May and produce well then the company will be forced to go to four day per
week rolling power cuts. He further stated that, barring rain soon, only one hydropower plant - Finchaa at 134 MW installed capacity, would be able to operate at full capacity. If this scenario comes to bear, then EEPCO will be forced to move to four day per week power cuts. ¶4. In addition to causing power outages, the rolling blackouts have other side effects. The optical fiber network distributor boxes used by the Ethiopian Telecommunications Company (ETC) require power from the grid to run outside of their short two-hour battery life. During the extensive power cuts now experienced, the boxes go out, essentially cutting off fixed-line telecommunications in the surrounding area. ETC is deploying mobile generators to keep some boxes charged, but do not have enough resources to locate generators permanently. ¶5. While a shortage of water is a natural consequence of drought, the power shortages are causing pumping stations to shut down. Thus, even if municipal water is available in Addis Ababa, it cannot reach homes or central faucets. A sight now common on power-cut days is urban dwellers traveling relatively far distances to obtain water. Also, with the intermittent pumping, contamination of drinking water with sewage is more likely. ¶6. No entity is exempt from the power cuts, including industry. While growth in high-energy consuming industries such as manufacturing has grown, accounting for some of the power deficit, the GoE is counting on these industries to help maintain economic growth. With extensive power cuts, those industries without large generators will be unable to meet production goals. ¶7. Help may be on the way soon, even if rains do not come. Two of the power plants in the GoE's ambitious hydropower expansion scheme were due to be on-line by now. Tekeze, which is located near the Eritrean border, has been delayed until next year due to an unexpected geological phenomena that was not detected in the feasibility study stage. When completed, Tekeze will have 225 MW of installed capacity. Gilgil Ghibe II was scheduled to be in service by now. However, this 184 MW plant has been delayed due to the difficulty of transporting large parts and equipment to its remote location southwest of Addis Ababa. In addition to upcoming hydropower projects, EEPCO is undertaking repairs on its 7 MW geothermal power plant at Aluto Langano and hopes to have it back on line in the next few months. ¶8. Comment: Ethiopia is sometimes known as the water tower of Africa, and for good reason. The potential for expansion of hydropower is significant. However, the current drought reveals the necessity (well acknowledged by EEPCO) for diversity of generation sources. Post will continue to monitor the impact of this year's drought on power generation and the economy as a whole. End ADDIS ABAB 00001229 002 OF 002 Comment. YAMAMOTO

Share this cable

 facebook -  bluesky -