Cable title:  

CAMISEA PIPELINE UPDATE: AUDITS

Tags:  ENRG ECON ETRD EAID SENV PE 
pdf how-to read a cable
VZCZCXYZ0003
RR RUEHWEB

DE RUEHPE #4480 3281956
ZNR UUUUU ZZH
R 241956Z NOV 06
FM AMEMBASSY LIMA
TO RUEHC/SECSTATE WASHDC 3084
RUEHQT/AMEMBASSY QUITO 0840
INFO RUEHBO/AMEMBASSY BOGOTA 4123
RUEHBR/AMEMBASSY BRASILIA 7099
RUEHBU/AMEMBASSY BUENOS AIRES 2682
RUEHCV/AMEMBASSY CARACAS 9960
RUEHLP/AMEMBASSY LA PAZ NOV SANTIAGO 0961
RUCPDOC/DEPT OF COMMERCE WASHINGTON DC
RUEATRS/DEPT OF TREASURY WASHDC
RUMIAAA/USSOUTHCOM MIAMI FL
RHEHAAA/NATIONAL SECURITY COUNCIL WASHINGTON DC
RHEBAAA/DEPT OF ENERGY WASHDC
UNCLAS LIMA 004480 

SIPDIS

SIPDIS

DEPT FOR WHA/AND, WHA/EPSC, OES
TREASURY FOR U/S TAYLOR, K. KOZLOFF, J. LEVINE
STATE PASS TO EXIM
DEPT OF ENERGY FOR S. LADISLAW
ENERGY INFORMATION ADMINISTRATION FOR CHARLES ESSER

E.O. 12958: N/A
TAGS: ENRG ECON ETRD EAID SENV PE
SUBJECT: CAMISEA PIPELINE UPDATE: AUDITS

REF: LIMA 0952

UNCLAS LIMA 004480 SIPDIS SIPDIS DEPT FOR WHA/AND, WHA/EPSC, OES TREASURY FOR U/S TAYLOR, K. KOZLOFF, J. LEVINE STATE PASS TO EXIM DEPT OF ENERGY FOR S. LADISLAW ENERGY INFORMATION ADMINISTRATION FOR CHARLES ESSER E.O. 12958: N/A TAGS: ENRG ECON ETRD EAID SENV PE SUBJECT: CAMISEA PIPELINE UPDATE: AUDITS REF: LIMA 0952 ¶1. SUMMARY: Three audits of Camisea pipeline construction and performance are in progress. The GOP contracted its audit to German firm Germanischer Lloyd, and a report is expected early next year. Camisea Consortium TGP delivered its internal audit report to the GOP, and a condensed version for public release is expected in the coming weeks. The Interamerican Development Bank (IDB) audit of environmental/social impacts should be completed by March 2007. Separate reports on pipeline sections for two of the liquids pipeline ruptures were completed, showing landslides as the cause of the ruptures. END SUMMARY. ¶2. After the fifth Camisea liquids pipeline incident in March (Reftel),the GOP's Energy Ministry (MEM) and Camisea pipeline consortium Transportadora de Gas Peruana (TGP) commissioned technical audits of the pipeline that are still in progress. The Interamerican Development Bank (IDB) commissioned an environmental/social audit that will not deal with engineering issues. The two technical audits are examining pipeline routing, construction issues and operations. While the audits are examining the gas pipeline, the focus is on the jungle portion of the parallel gas liquids pipeline that has suffered five integrity incidents since gas and liquids began flowing in August 2004. ¶3. The MEM evaluated eleven bidders for the GOP audit, and in September awarded a $1.9 million contract to the Mexican subsidiary of the German technical monitoring firm Germanischer Lloyd; the contract was finalized October 17. Germanischer Lloyd Peru officials told Econoff that the firm was under strict instructions not to discuss the audit with third parties. Gustavo Navarro, MEM Hydrocarbons director and the GOP overseer of the audit contract, told Econoff that the audit was progressing but no report was expected until February. He noted that the MEM, TGP and Banco de Credito had finalized an agreement to fund the audit. TGP Chief of Corporate Relations Rafael Guarderas confirmed that Germanischer's work was proceeding and that TGP was organizing field visits for the firm in December. ¶4. Guarderas also reported on TGP's internal audit. TGP has spent $40 million over the last eight months and employed 1500 workers to analyze and perform corrective maintenance to the entire pipeline system. TGP used robotic "pigs" to travel the inside of each section. It found anomalies in 30 pipe sections out of about 48,000 sections in total; most of the anomalies were gashes and none indicated significant risk of rupture. TGP has issued its report to the MEM and is preparing a condensed version of the report which will be released to the public. ¶5. Two pipeline sections involved in rupture incidents were removed from the system to undergo physical analysis. One section, from the November 2005 incident, fell into a river and TGP workers could not extricate it until this Spring. The other section, from the March 2006 rupture, was sent to Texas engineering firm MCI for analysis. Reports on both sections revealed that environmental pressures (landslides) and not structural or welding defects caused the sections to break. ¶6. The IDB is funding its own environmental and social audit (AASI) of the Camisea project as part of its 2003 loan commitment; this audit will not deal with engineering aspects of the pipeline. AASI auditors are in the field now, and the final report is expected in March 2007. COMMENT -------------- ¶7. (U) The results of the various pipeline audits will be important to assess lessons learned from the past, but looking to the future is even more important. TGP has been in a constant process of refining the pipeline routing and reinforcement. The rainy season that has just begun will be the test of TGP's improvements, as all of the incidents have occurred during the November to April rains when waterlogged earth exerts pressure on the pipes. STRUBLE