06BUENOSAIRES2594
2006-11-20 19:25:00
UNCLASSIFIED//FOR OFFICIAL USE ONLY
Embassy Buenos Aires
Cable title:  

DUKE ENERGY BETS ON GROWING ARGENTINE ELECTRICITY

Tags:  ECON ENRG EPET AR 
pdf how-to read a cable
VZCZCXYZ0000
OO RUEHWEB

DE RUEHBU #2594/01 3241925
ZNR UUUUU ZZH
O 201925Z NOV 06
FM AMEMBASSY BUENOS AIRES
TO RUEHC/SECSTATE WASHDC IMMEDIATE 6534
INFO RUEHAC/AMEMBASSY ASUNCION PRIORITY 5745
RUEHBO/AMEMBASSY BOGOTA PRIORITY 1452
RUEHCV/AMEMBASSY CARACAS PRIORITY 1000
RUEHLP/AMEMBASSY LA PAZ NOV 4324
RUEHPE/AMEMBASSY LIMA PRIORITY 1904
RUEHME/AMEMBASSY MEXICO PRIORITY 1244
RUEHOT/AMEMBASSY OTTAWA PRIORITY 0428
RUEHFR/AMEMBASSY PARIS PRIORITY 1158
RUEHQT/AMEMBASSY QUITO PRIORITY 0794
RUEHSG/AMEMBASSY SANTIAGO PRIORITY 5356
RUEHSO/AMCONSUL SAO PAULO PRIORITY 3039
RUEAIIA/CIA WASHINGTON DC PRIORITY
RHMFIUU/DEPT OF ENERGY WASHINGTON DC PRIORITY
RUEHC/DEPT OF LABOR WASHINGTON DC PRIORITY
RUEATRS/DEPT OF TREASURY WASHINGTON DC PRIORITY
RHMFIUU/HQ USSOUTHCOM MIAMI FL PRIORITY
RHEHAAA/NATIONAL SECURITY COUNCIL WASHINGTON DC PRIORITY
RUCPDOC/USDOC WASHINGTON DC PRIORITY
UNCLAS BUENOS AIRES 002594 

SIPDIS

SENSITIVE
SIPDIS

WHA FOR WHA/BSC AND WHA/EPSC
E FOR THOMAS PIERCE,
PASS NSC FOR JOSE CARDENAS
PASS FED BOARD OF GOVERNORS FOR PATRICE ROBITAILLE
EX-IM BANK FOR MICHELE WILKINS
OPIC FOR GEORGE SCHULTZ AND RUTH ANN NICASTRI
PASS USTR FOR SUE CRONIN AND MARY SULLIVAN
TREASURY FOR ALICE FAIBISHENKO
USDOC FOR ALEXANDER PEACHER AND JOHN ANDERSEN
USCINCSO FOR POLAD

E.O. 12958: N/A
TAGS: ECON ENRG EPET AR
SUBJECT: DUKE ENERGY BETS ON GROWING ARGENTINE ELECTRICITY
DEMAND, EVENTUAL REGULATORY NORMALIZATION


This cable contains U.S. company-specific commercially
sensitive information.

-------
Summary
-------

UNCLAS BUENOS AIRES 002594

SIPDIS

SENSITIVE
SIPDIS

WHA FOR WHA/BSC AND WHA/EPSC
E FOR THOMAS PIERCE,
PASS NSC FOR JOSE CARDENAS
PASS FED BOARD OF GOVERNORS FOR PATRICE ROBITAILLE
EX-IM BANK FOR MICHELE WILKINS
OPIC FOR GEORGE SCHULTZ AND RUTH ANN NICASTRI
PASS USTR FOR SUE CRONIN AND MARY SULLIVAN
TREASURY FOR ALICE FAIBISHENKO
USDOC FOR ALEXANDER PEACHER AND JOHN ANDERSEN
USCINCSO FOR POLAD

E.O. 12958: N/A
TAGS: ECON ENRG EPET AR
SUBJECT: DUKE ENERGY BETS ON GROWING ARGENTINE ELECTRICITY
DEMAND, EVENTUAL REGULATORY NORMALIZATION


This cable contains U.S. company-specific commercially
sensitive information.

--------------
Summary
--------------


1. (SBU) Duke Energy plans to upgrade and expand its two
hydro and gas-fired electricity generating plants in Neuquen
province and possibly make new generating capacity
acquisitions in the domestic market. In a call on Ambassador
Wayne, Duke executives explained that they see the Argentine
electricity market as a promising long term play, with growth
potential superior to that of Duke's mature U.S. domestic
electricity market. Duke takes this position in the face of
an interventionalist Argentine regulatory regime in which the
availability of natural gas to fire its combined cycle plant
is not assured and in which the GoA-controlled energy
wholesaler has shortchanged the company over $25 million on
hydro and gas electricity generation payments. Further, the
GoA has forced Duke and other generators to convert this GoA
debt into equity in a new GoA generating facility fiduciary
fund. The GoA has promised to normalize its electricity
market regulation beginning in 2008. End Summary


2. (U) Duke Energy Southern Cone COO Laine Powell and
Argentina Country Manager Guillermo Fiad met with Ambassador
November 15 to review Duke's operations in Argentina and to
discuss Duke,s electricity generation investment strategy in
Argentina, including its forced investment in GoA generation
fiduciary funds, its plans to upgrade and expand existing
Neuquen province hydro and gas-fired plants, and possible new
generating sector acquisitions in the domestic market.

--------------
Duke Energy in Argentina
--------------


3. (U) Duke Energy Argentina, a subsidiary of Duke Energy
International, owns two power generating assets in Neuquen
province: The Planicie Banderita hydroelectric power station

produces 476 MW and the Alto Valle gas-fired thermal station
produces 80 MW. Duke also began conducting licensed trading
and marketing in the wholesale electric and natural gas
markets in late 2000.


4. (SBU) Powell noted that, to meet the company's global
energy generation growth targets of 4-6% a year, Duke is
looking to expand its presence in Argentina, Central America,
Peru and Brazil. As a result, in recent discussions with
Planning Minister De Vido, Duke committed to upgrade its Alto
Valle gas-fired plant to bring 17 MW of unused capacity on
line. In return, Duke asked De Vido to commit to lock-in
scarce natural gas supplies for this plant. Duke has also
submitted to Energy Secretary Cameron plans to invest roughly
$60 million to add 37MW of new generating turbines to its
Neuquen hydro plant if an appropriate package of federal and
provincial tax incentives can be negotiated. Powell noted
that, given his company's positive view on long term local
market development prospects, Duke is exploring new
generation acquisitions in Argentina. The company's strategy
is to purchase existing single cycle gas-fired generation
plants and upgrade them to combined cycle operations (where
significant efficiency gains are realized by capturing waste
heat).

--------------
Duke's Strategy: A Non-Confrontational Stance
--------------


5. (SBU) Unlike a number of other U.S. energy sector players
here, including CMS Energy, Duke did not file an ICSID claim
seeking compensation for the (1) pre-emergency law de-linking
of power tariffs from the U.S. producer price index; and (2)
post-emergency law pesification of generation capacity cost
and variable cost payments by regulated electricity
wholesaler CAMMESA. (Note: Pre-crisis capacity payments to
generators were roughly US$10/MW while current payments total
roughly $4/MW). Country Manger Fiad called this the right
decision for a company that sees long term growth
opportunities in the Argentine energy market.

--------------
Forced Fiduciary Fund Investment
--------------


6. (U) With voluntary private investment in new electricity
generating capacity limited by GoA price controls and
investor concerns over rapid GoA shifts in sector regulation,
the GoA created a fiduciary fund, FONINVENMEM (Fondo de
Inversiones en Mercado Electrico Mayorista - Fund for
Investment in the Wholesale Electricity Market) to force new
investment by generators in two new 800 MW combined cycle
plants in Buenos Aires and Santa Fe provinces. The plants
will cost USD 1.2 billion, of which USD 450 million is being
funded by the forced swap of outstanding CAMMESA debt to
generators into FONIMVENMEM equity. This debt results from
longstanding shortfalls in required marginal cost CAMMESSA
payments to generators. The GoA has stated that the
remaining $750 million would be funded via a 3-4% surcharge
on medium and large electricity users over the next 5 years,
via private pension fund financing and via new investors.


7. (U) Generators, share of forced FONINVENMEM investment is
based on their share of domestic generating capacity.
Duke,s share of the USD 450 million generators,
"investment" is 5%. France,s Total (which just announced the
sale of its Argentine generating assets to a local group and
to Merrill Lynch) holds 28%, Spain,s Endessa holds 23%, AES
holds 15% and Petrobras holds roughly 10%. In exchange for
this forced investment, the GoA has committed to (1) have
energy wholesaler CAMMESA sign a power purchase agreement to
guaranty the profitability of the two new plants; (2) secure
dedicated gas supplies to supply the new plants; and (3)
eventually transition to a free market in energy tariffs
after the two new plants come on line in 2008.

--------------
Comment
--------------


8. (SBU) While Duke executives acknowledge the many
inefficiencies, uncertainties and electricity production
risks inherent in the GoA's interventionalist approach to
managing Argentina's energy sector, they continue to see the
Argentine market as one with promising medium term prospects.
A legacy of major energy sector investment in the 1990s has
left Argentina with a relatively modern electricity
generation, transmission and distribution infrastructure.
Populist post-2002 crisis GoA policies have kept consumer and
industrial end-use electricity prices far below world market
levels. Not surprisingly, this has led to significant
increases in electricity demand. Argentina's national grid
is now reaching the limit of its capacity and new generating
facilities are desperately needed. Despite regulatory
uncertainty, Duke is betting this looming shortage spells
opportunity. End Comment
WAYNE