Identifier
Created
Classification
Origin
03RANGOON178
2003-02-10 02:52:00
CONFIDENTIAL
Embassy Rangoon
Cable title:  

BURMA'S ENERGY POLICY: BETTER LUCKY THAN GOOD

Tags:  ENRG ECON EINV BM 
pdf how-to read a cable
This record is a partial extract of the original cable. The full text of the original cable is not available.
C O N F I D E N T I A L SECTION 01 OF 03 RANGOON 000178 

SIPDIS

STATE FOR EAP/BCLTV, EB/ESC
COMMERCE PASS ITA JEAN KELLY
TREASURY PASS OASIA JEFF NEIL
CINCPAC PASS FPA

E.O. 12958: DECL: 02/09/2013
TAGS: ENRG ECON EINV BM
SUBJECT: BURMA'S ENERGY POLICY: BETTER LUCKY THAN GOOD

REF: A. 02 RANGOON 1340

B. 02 RANGOON 651

C. 01 RANGOON 1819

D. 01 RANGOON 783

Classified By: COM CARMEN MARTINEZ FOR REASONS 1.5 (B,D)

C O N F I D E N T I A L SECTION 01 OF 03 RANGOON 000178

SIPDIS

STATE FOR EAP/BCLTV, EB/ESC
COMMERCE PASS ITA JEAN KELLY
TREASURY PASS OASIA JEFF NEIL
CINCPAC PASS FPA

E.O. 12958: DECL: 02/09/2013
TAGS: ENRG ECON EINV BM
SUBJECT: BURMA'S ENERGY POLICY: BETTER LUCKY THAN GOOD

REF: A. 02 RANGOON 1340

B. 02 RANGOON 651

C. 01 RANGOON 1819

D. 01 RANGOON 783

Classified By: COM CARMEN MARTINEZ FOR REASONS 1.5 (B,D)


1. (C) Summary: Burma may have found a patch for its energy
problems in 2003. A slower decline at the aging A'Pyauk gas
fields (about 50 miles north northwest of Rangoon),
unexpectedly large finds of gas in the recently developed
Nyaungdon field (about 20 miles northwest of the capital),
and better than expected performance by the pipeline from
Kanbauk (in Tanintharyi Division) to Hpa'an (in Kayah State)
and Rangoon, apparently have lifted supplies of gas in lower
Burma from 114 mcfd in early 2002 to perhaps as much as 178
mcfd by the end of February 2003. Some of these numbers are
still soft, but, the overall supply of gas and electricity
should be better (and perhaps far better) in Rangoon in 2003
than it was in 2002. There may also be some substantial
savings of foreign exchange (perhaps as much as $100 million)
on anticipated oil imports that now will not be required.
Longer term (meaning 2004),the GOB is banking on hydropower
to meet its energy needs. By the end of 2003, the Ministry
of Electric Power hopes to have an additional 355 megawatts
of hydropower generating capacity on line, as well as a new
125-megawatt coal-fired plant. If successful, that could
produce the first balance between electricity supply and
demand in Burma that anyone has seen for many years. However,
it is still too soon to declare Burma's energy crisis over.
If the new found gas gives out before the GOB can bring on
line its planned hydropower plants, Burma could find itself
saddled in late 2003 and early 2004 with the same sort of
shortages that plagued life here in 2002. End summary.

The GOB's Got Gas...


2. (C) Burma may not face the same problems with electricity
supplies during the dry season of 2003 as it did in 2002.
When we reviewed Burma's energy balance last year, the
situation looked grim (see Ref B). Nationwide demand for
natural gas stood at 234 million cubic feet per day (mcfd),

while supplies were estimated at only about 114 mcfd because
of the rapid decline in production in the A'pyauk fields,
which had always provided the vast majority of Burma's
onshore gas. The net result was that gas supplies were not
even sufficient to meet the demands of Burma's gas-fired
electricity generating facilities, much less that of the
country's urea, methanol, steel, and other plants. The GOB,
as a result, was obliged to shut down a good portion of its
industrial capacity and convert a number of its gas-fired
generating plants to diesel. Even so, day-to-day electricity
generating capacity dropped to between 550 and 600 megawatts
during the dry season of 2002; i.e., to only 65 to 70 percent
of Burma's estimated 800 to 840 megawatt demand. Blackouts
and brownouts became the rule throughout lower Burma,
including Rangoon.


3. (C) Since then, however, the GOB appears to have hit a
stretch of luck. While production at the A'pyauk fields
continues to decline, from 116 mcfd in 1998 to about 35 mcfd
today, the GOB's development of the Nyaungdon field has gone
far better than anyone predicted. Late last year, that field
was producing only about 25 mcfd. This year, according to
government press releases, new discoveries have pushed
production at Nyaungdon's 14 wells to more than 60 mcfd.
According to Ministry of Electric Power planners, GOB workers
are working overtime to replace the current 8-inch pipeline
with one sufficient to carry the larger flow. Reportedly,
that new, larger capacity pipeline should be ready by the end
of February.


4. (C) At the same time, the pipeline which the government
installed to carry gas from the Yadana export pipeline at
Kanbauk to Hpa'an (later extended to Rangoon) has apparently
performed far better than expected. When the pipeline was
first completed in 2001, most western experts judged it would
never carry more than 10 to 20 mcfd, given its poor quality
and contract terms which guaranteed only 20 mcfd to the
government. However, the Ministries of Energy and Electric
Power now claim that they are pushing 50 mcfd through the
pipeline -- more than enough to meet the demand of the new
cement plant at Hpa'an while still leaving supplies for
Rangoon's electricity facilities.

5. (C) The net result of these developments is that Burma
could have 60 mcfd to 70 mcfd of additional gas over and
above levels in early 2002, even after allowing for the
decline in production in the A'pyauk field. In fact,
assuming the best-case scenario, the GOB could have available
as much as 178 mcfd of natural gas (128 mcfd being the total
onshore production of gas from all fields including A'Pyauk
and Nyaungdon, plus 50 mcfd from offshore) -- a level not
seen since 1998.

...But Will the Juice Flow?


6. (C) Of course, it remains to be seen how real and how
sustainable these increased supplies will prove to be. The
full 60 mcfd of gas from Nyaungdon has yet to arrive in
Rangoon. Furthermore, the Nyaungdon field in particular
appears to have been developed entirely with a focus on the
economy's short-term needs, without any attention to
sustainability. If the development program has been too
aggressive, then that field too could peter out (as the
A'pyauk field has) far sooner than the GOB now expects.


7. (C) In the case of the Kanbauk-Hpa'an-Rangoon pipeline,
there are two issues: contract terms and durability. The GOB
may now be drawing more than the 20 mcfd it is entitled to
under its contract. However, if it is, it is probably
because of a short-term quirk in the system. It is possible
that Thailand cannot, for technical reasons, use all of the
pre-paid gas that it has available in the stock it has built
up under its "take or pay" contracts. Producers in the
second major offshore gas field, Yetagun, may also not yet be
ready to use their full share of the pipeline's capacity. If
not, this may allow for additional gas to be pumped, from the
Yadana field, for Burmese consumption. In either case, Burma
could shortly find itself squeezed back to the 20 mcfd to
which it is actually entitled, as Thai drawings increase
and/or Yetagun production comes up to full capacity. As for
durability, the pipeline was not built to the highest
standards. In fact, the most common prediction at the time
it was completed was that it would blow up or blow out every
time it was filled. That, in fact, was the result during its
first weeks of operation. Since then, it has settled down,
but there is still the risk that an accident will take the
pipeline down for several weeks or months.


8. (C) Nevertheless, the bottom line now is that the lights
are on in Rangoon and they could stay on throughout the dry
season, if the augmented supplies of gas can be sustained.
Since October, there have been occasional outages, but we
have not had anything like the rolling blackouts that plagued
Rangoon during 2002's dry season. Equally importantly, if
the GOB has been able to bring an additional 60 to 70 mcfd of
gas on-line since early 2002, there will be major savings of
foreign exchange. Each 22 mcfd of gas effectively translates
into 1 million barrels per year of diesel fuel. At current
prices, consequently, an additional supply of 65 mcfd of gas
would mean potential savings of up to 3 million barrels per
year of diesel worth approximately $100 million - $120
million. It would also mean less downward pressure on the
kyat, which at 1100 kyat/dollar, is still running well above
the 1200 to 1400 kyat/dollar rate that we predicted for the
end of 2002 and the beginning of 2003.

I've Got One Word For You: Hydropower


9. (C) The Ministry of Electric Power asserts that the
long-term solution to all these uncertainties and stop-gap
solutions is hydropower. According to the Ministry's
Director General for Planning, there is now 390 mw of
installed hydropower capacity in Burma, but this is only
about 1 percent of Burma's estimated potential. In its most
recent 5-year plan, the GOB set the ambitious goal of
installing an additional 2000 mw of hydropower capacity by
2006 (pie in the sky at best). Unlike many older hydropower
plants, which are located in remote border or mountainous
areas, many of the new plants are to be constructed in river
valleys closer to the main power grids around Mandalay and
Rangoon. Mini-hydropower and other small plants will also be
built to electrify more rural areas.

10. (C) The DG admitted that for the next two years, the
objective is to patch as quickly as possible current energy
shortages. Thus, planners hope that by the end of 2003 the
Ministry's Myanmar Electric Power Enterprise (MEPE) will have
completed two hydropower plants with a combined 355-mw
capacity (the Paunglaung dam in southern Mandalay Division
with 280 mw, and the Mone dam in central Magway Division with
75 mw). They also hope to bring on line one coal-fired
thermal plant with 125-mw capacity. This additional
capacity, once plugged into the grid could make up the
current deficit in power production in lower Burma, while
replacing imports of diesel, and reducing the GOB's exposure
to gas supplies. By 2005, the planners estimate, the new
hydropower capacity should be well ahead of total demand,
allowing strategists to ponder longer-term energy plans.

Comment


11. (SBU) If all goes as planned, for the next several months
at least supplies of gas and electricity to the capital
should top the levels available in 2002. If the planned
hydropower is actually installed and available as predicted,
then this additional gas supply may in fact bridge the gap.


12. (C) Of course, there will still be a case for the
construction of a major pipeline to bring Burma's offshore
gas onshore for domestic use, if only to fuel now idled
industrial facilities. However, accessing that gas will not
be the sort of critical political event that finding supplies
of fuel was this year. Had the citizens of Rangoon had to
spend one more season in the dark with living standards
undermined by a rapidly depreciating kyat, this government
truly could have been in trouble. Even now, it's not secure,
but with the energy situation now apparently under control,
at least to some degree, it may have more breathing space
than we anticipated several months ago.
Martinez