03ANKARA753
2003-01-29 17:56:00
CONFIDENTIAL
Embassy Ankara
Cable title:  

BTC UPDATE FROM TURKEY

Tags:  ENRG ECON EPET AJ GG KZ TU 
pdf how-to read a cable
This record is a partial extract of the original cable. The full text of the original cable is not available.
C O N F I D E N T I A L ANKARA 000753 

SIPDIS


STATE FOR E, EB/CBED, EB/ESC, EUR/SE
STATE PASS NSC FOR QUANRUD AND BRYZA
USDOC FOR 4212/ITA/MAC/OEURA/CPD/DDEFALCO
USDOE FOR PUMPHREY/ROSSI


E.O. 12958: DECL: 08/08/2012
TAGS: ENRG ECON EPET AJ GG KZ TU
SUBJECT: BTC UPDATE FROM TURKEY

REF: ANKARA 528


Classified by EconCouns Scot Marciel, Reason 1.5 (b,d)


C O N F I D E N T I A L ANKARA 000753

SIPDIS


STATE FOR E, EB/CBED, EB/ESC, EUR/SE
STATE PASS NSC FOR QUANRUD AND BRYZA
USDOC FOR 4212/ITA/MAC/OEURA/CPD/DDEFALCO
USDOE FOR PUMPHREY/ROSSI


E.O. 12958: DECL: 08/08/2012
TAGS: ENRG ECON EPET AJ GG KZ TU
SUBJECT: BTC UPDATE FROM TURKEY

REF: ANKARA 528


Classified by EconCouns Scot Marciel, Reason 1.5 (b,d)



1. (C) Summary: BTC construction in Turkey is on schedule
(first pipe is scheduled to arrive at Iskenderun port on
February 7) and on budget; however, there is some concern
that the change in government has slowed down the
decision-making process on operational issues. We believe
that occasional delays are to be expected in a project of
this size; however, we will meet with GOT officials in the
next several days to reiterate the importance of operational
continuity for BTC. End summary.



2. (C) Although BTC construction in Turkey is on schedule and
on budget, BOTAS General Manager Bildaci and Turkey-based BTC
Co executives are concerned that the change in government has
slowed down the decision-making process on operational
issues. Bildaci and BTC Co officials complained to econoff
that BOTAS employees and board members are "paralyzed" as
they wait for the outcome of rumored personnel changes and
new investigations into past contract awards. For example,
Bildaci claimed that the board has delayed voting on hiring
additional personnel to handle the logistics of land
acquisition, and BOTAS employees are neglecting important
BTC-related issues as they investigate claims by the new
government that BTC Co salaries are too high.



3. (C) AK Party officials -- from Tayyip Erdogan to Energy
Minister Guler -- have emphasized their support for the BTC
project (reftel). At the same time, however, the new
government has reportedly taken steps that have caused some
jitters at the Ministry of Energy (MENR) and BOTAS. For
example, the government reportedly wants to investigate all
past tenders and contract awards made by BOTAS. A recent
television news report stated that Energy Minister Guler had
sent to the President's office for approval a decree
dismissing the top 50 energy bureaucrats, including the
Energy Undersecretary and Deputy Undersecretaries, as well as
the Director General and Deputy Director General of BOTAS,
TPAO, and other state-owned energy companies. (Note:
Neither our MFA or MENR contacts can confirm the existence of
this decree or who is on it.)



4. (C) On the positive side, the first pipe for the Turkish
segment of BTC is scheduled to arrive at Iskenderun port on
February 7. For now, BOTAS is planning to receive all pipe
at Iskenderun; however, it has designated other "contingency"
ports in the event that regional developments close the
Iskenderun option.



5. (C) Local BP executives told econoff that, as of February
1, BP will increase the risk level for Turkey from "medium"
to "high." The next risk level of "very high" could result
in the evacuation of BP expats from Turkey.



6. (C) Comment: As noted, BTC construction in Turkey is on
track; we believe that current operational delays --although
not to be ignored -- are one of the to-be-expected hiccups in
a project of this size. We will meet with MFA Deputy U/S
Kilic and Ministry of Energy U/S Yigitguden in the next
several days to reiterate the importance of operational
continuity for BTC. End comment.
PEARSON